Zeyad Al Khoshaim Law Firm (ZKLF) Olaya Tower B
A high quality fit-out project constructed by Absal Paul from ‘grey box’ stage to a fully functioning corporate headquarters within a 16 week timeframe. Works consisted of full M.E.P., partitions, specialist wall and ceiling finishes, signage, low current installations and fitted furniture.
PROJECT TEAM
Client: Zeyad Al Khoshaim Law Firm (ZKLF)
Project Team: Bluehaus Group (Designer) & AECOM (PM and Cost Consultant)
PROJECT DETAILS
Location: Riyadh, Saudi Arabia
Completion Date: December 2015
Contract Value: SAR 12 Million
Floor Area: 1400 m2
Duration: 16 weeks