B&B Logistics
Construction of a new logistics facility at Bahrain Logistics Zone containing significant cold storage area, marshalling yard, dock levellers, administration space, external parking and all associated ancillary buildings and services.
- Stone pile ground improvement beneath entire structure
- DM2 rated steel fibre reinforced concrete floors to accommodate racking and associated forklift movement
- Extensive cold storage (chilled & frozen) with all other areas fully conditioned to meet customer requirements
PROJECT TEAM
Client: B&B Logistics WLL
Architect: Elevations AE
Structural Engineer: Elevations AE
Services Engineer:
Quantity Surveyor: DG Jones
PROJECT DETAILS
Floor Area: 10,000m2
Start Date: November 2017
Completion Date: December 2018
Programme: 56 weeks